Water Transmission Main Bid Package 7A.
This project will consist of the installation of a water transmission main traveling through Orland Park at 70th Court and Wheeler Drive. The water transmission main will be installed via the open cut method. Construction will be starting near the intersection of 157th Place and Oak Park Avenue in Tinley Park with work in Orland Park anticipated to start the week of September 16, 2024.
This project is an extension of previous water main construction done on Wheeler and will be conducted by the same contractor. Work is estimated to take several months, with repaving to take place in Spring of 2025. Traffic is expected to be maintained throughout the duration of the project, with short and intermittent road closures as needed.
The Village of Oak Lawn Regional Water System (RWS) is upgrading and expanding its ability to provide Lake Michigan water to the residents of the Southwest Suburbs including the Village of Orland Park. As part of these improvements, a new Water Transmission Main and Intake Structure will be constructed within the area bordered by 151st Street, Catalina Drive, Wheeler Drive / ComEd right-of-way and Liberty Park / Raintree Drive.
Transmission Main will be installed in the ComEd Right-of-Way South of 82nd Avenue to Catalina Drive with potential impacts to residents on:
- Anne Drive
- Primrose Court
- Tulip Court
- Orchid Court
- Sunflower Court
- Halesia Court
To access the announcement flyer with additional details, please follow this link.
The Village of Orland Park is a member of the Regional Water Supply (RWS) system. RWS is a group of 12 communities that receive water from the Village of Oak Lawn, who receives Lake Michigan water from the City of Chicago. The Village’s existing water infrastructure is close to 40 years old and the Village has been working with RWS for several years to install a redundant water supply line from Oak Lawn. This water line is called Spur 2 and it will serve as a redundant water line for the Village.
To view the progress of this project, follow this link to a video.
Construction started in late 2023 and projected to be completed by 2025.
It is anticipated that the pipeline work will be completed by the middle of July and roadway repair work will be completed by the end of August. These estimated timelines may change due to weather, availability of contractors and materials.
UPDATE (8/19/2024): Binder was completed on Wheeler, Raintree, 82nd Street and Thistlewood over the weekend. The top layer is scheduled to be placed on Tuesday, August 20, 2024.