Permit Application Requirements
You will be required to draw on a copy of the plat, the shape, dimensions, and placement of the concrete that you are adding. A permit is required for all flat work, including but not limited to driveways, patios, sidewalks, garage floors, etc.
Due to weather conditions in our region, the Village of Orland Park has a cut off date for exterior concrete flat work. This period will begin on November 15th and extend to March 15 for flat work which typically includes driveways, sidewalks, and exposed slabs on grade. For more information on Cold Weather Requirements and Restrictions.
Refer to the Village Code Title 5, Chapter 1, Section 109.3.7 for inspection requirements and Section 109.3.7.1 for cold weather requirements.
A pre-pour inspection of the base stone and forms is required. A final inspection is required once the work has been completed. A 24-hour notice is required for all inspections. View the concrete inspection request form.
For detailed requirements on sidewalks and driveways see: Land Development Code Section 6-406, Sidewalks, Driveways, and Parking Lots.